Tacoma Municipal Building Exterior Preservation Project

Contact
David Pagel
Engineering Project Manager
(253) 591-5267
dpagel@tacoma.gov
The exterior of the Tacoma Municipal Building has undergone various assessments to identify cleaning and preservation needs. Prior to City ownership the building was sandblasted multiple times for cleaning. The sandblasting removed the smooth finish from the cast stone, causing it to become more porous. This has led to accelerated deterioration, including organic growth, water intrusion, cracking, and spalling.
Based on the completed assessments, full refurbishment of the building exterior is anticipated to exceed $20 million. Preservation of the building exterior will be completed through a phased approach. The City has allocated $4.5 million for the first phase, with ongoing efforts to secure additional funding for future phases.
Building History
- Officially dedicated January 29, 1931, as the Rhodes Medical Arts Building, the Tacoma Municipal Building is listed on local, state, and National Registers of Historic Places.
- The City purchased the building c. 1976, and the first City Council meeting was held on December 18, 1979.
Project Timeline
-
May 2021
-
A comprehensive assessment of the building exterior was completed by Richaven Architecture & Preservation.
-
July 2024
-
Additional observations were conducted by Wiss, Janney, Elstner Associates, Inc. (WJE) to develop construction documents for the Phase 1 work.
-
Spring 2025
-
- On March 26, 2025, the project was presented to the Landmarks Preservation Commission.
- The initial phase will focus on cleaning and preservation work to the cast stone on the east façade (St. Helens) and west façade (Market Street) and is currently posted for competitive solicitation on our Purchasing & Solicitations web page.
-
Summer 2025-End of 2026
-
- Phase 1 work is scheduled to start in summer 2025 and is anticipated to be completed by the end of 2026.
- Knowledge gained will inform the scope of future phases. Including means and methods, refined quantities, durations, and estimated costs.
- Continue to seek funding opportunities to implement Phase 2 through the City budgeting process, legislative requests, and grant opportunities, including the State Heritage Capital Projects (HCP) grant program.
-
2027
-
Phase 2 will begin and will prioritize cleaning and preservation work on the south and north façades.