Permitting Marijuana Businesses
Marijuana Businesses 101
-
Recreational marijuana is categorized into three uses:
- Production – The growing and harvesting of marijuana
- Processing – Packaging marijuana and creation of marijuana infused products
- Retail – Sale of marijuana products to the general public
*Please note that permitting and approval needs will vary depending on the type of business and the alterations needed for the building.
-
Certain locations within the City allow these uses, subject to City zoning requirements and 1,000 foot separation requirements from the following uses:
- Elementary Schools & Secondary Schools
- Playgrounds
- Public Parks (500 feet for retail in downtown)
- Recreation/Community centers & Libraries (500 feet for retail in downtown)
- Child Care Centers (500 feet for retail in downtown)
- Game Arcades (500 feet for retail in downtown)
- Correctional Facilities & Court Houses (500 feet for retail in downtown)
- Drug Rehabilitation Facilities, Substance Abuse Facilities, & Detoxification Centers (500 feet for retail in downtown)
- Public Transit Centers (100 feet for retail uses only)
A general map indicating where approved recreational marijuana locations are within the City may be found here.
To verify a specific address, call a City Planner at (253) 591-5030 (select “commercial” project on the phone system) or email zoning@tacoma.gov.
-
- City of Tacoma – Business License
- City of Tacoma – Applicable Permits
- Tacoma-Pierce County Health Department (TPCHD)
- Building Certificate of Occupancy
- Washington State Liquor & Cannabis Board (WSLCB)
- Puget Sound Clean Air Agency (PSCAA)
Note: These approvals are for the marijuana business holistically
Steps to Getting a Building Permit
If you’re planning to open or modify a marijuana business in an existing building, you may need a building permit before making changes to the property. This applies to marijuana producers, processors, and retailers.
A building (BLDCA) permit may be required if your project involves changes to:
- Use or occupancy of the building/property;
- Interior or exterior alterations to the building;
- Doors, windows, flooring, or walls;
- Plumbing, drains, electrical wiring or plugs;
- Mechanical systems, fans, or ventilation;
- Siding, roof work, paving/gravel, parking restriping; or
- Implementation of an extraction process.
The sections below provide guidance on getting started, planning your project, and navigating the permitting process.
-
- Review the site location.
- Contact the Washington State Liquor and Cannabis Board, Puget Sound Clean Air Agency, and Tacoma-Pierce County Health Department and determine what other approvals are necessary.
- Review Building Code requirements
- Prepare a floor plan and site plan.
- Think about any necessary utility service, work, or upgrades that you will need to operate the business (i.e. power upgrade, electrical/lighting work, water service, fire sprinklers, gas connection).
- Prepare a Traffic Generation Worksheet and Source Control worksheet.
- Submit a Pre-Application Request online through the Accela- Tacoma Permits Portal.
-
- Occupancy Groups:
- F-1* for growing, processing, and packaging (liveload of 125 psf)
- S-1* for storage of supplies and finished product (liveload of 125 psf)
- B for office
*If a change of use or occupancy is being proposed and the building includes a fire area exceeding 12,000 square feet, fire sprinklers are required for F-1 and S-1 occupancies. (See IEBC 1012.2, IBC 903.2.4, and 903.2.9)
- Floor plans should include all walls, plastic covering (if permitted), and fixtures.
Plastic Sheeting must have:
- A flame spread index of less than 200, and
- A smoke developed index of less than 450 (UL 723 Class C or better).
- All other requirements apply such as fire separations, exiting, ADA accessibility, and plumbing facilities.
-
- A step-by-step narrative of all processing methods — Specifications of the processing equipment should be included.
- A Hazardous Materials Inventory Statement (HMIS) (See IFC 5001.5.2)
- Specifications of carbon dioxide enrichment equipment
-
- A seismic evaluation and upgrade could be required with change of occupancy.
Anchorage will need to be considered for lateral loading.
- Substantial frames/supports are required for lighting.
- Storage rack design will need to be detailed.
Show the height from the floor to the top of the storage materials.
-
- Show all proposed plumbing fixtures (i.e. number and type) with riser diagram.
- Provide details regarding groundwork, side sewer, and source control.
- Review Source Control Plan
-
- Heating is required for occupied spaces
(See IBC 1204.1).
Ventilation details, including location of ventilation shafts and output – 0.06 CFM/SF (Cooling Air Flow per Square Foot) is required for warehouses.
- Heating is required for occupied spaces
-
- ADA Parking, accessible route of travel to the primary use/work areas, restrooms
Quick Links
- Accela – Permit platform
- Building Certificate of Occupancy (issued by the City once all required final inspections are completed and approved)
- Fee Estimator
- Permit Timeline
- City of Tacoma – Business License
- City of Tacoma – Applicable Permits
- Tacoma-Pierce County Health Department (TPCHD)
- Washington State Liquor & Cannabis Board (WSLCB)
- Puget Sound Clean Air Agency (PSCAA)
- Food, Beverage, and Production Businesses (in-progress)
- Grease Interceptors (in-progress)
- Water Line and Discharge (in-progress)
- Parking (in-progress)
- Commercial Alterations and New Construction (in-progress)
Additional Resources
- To verify a specific address, call a City Planner at (253) 591-5030 (select “commercial” project on the phone system) or email zoning@tacoma.gov.